Catalogue / Site acceptance & pre-commissioning tests

No photo yet

Pre-commissioning tests for substations, Eco seriesSample

by Kamrup Projects (Sample) · verified by BARREL

Price for verified buyers

Ordered and invoiced through BARREL — one contract, one GST invoice.

Customise and request quote

Made to order: change the marked specification rows to what you need; Kamrup Projects (Sample) quotes for it.

Or send an open RFQ to every matching merchant.

Register your company to see prices.

The Eco service of pre-commissioning tests for substations by Kamrup covers 5 plant size options (5 MW to 100 MW). Highlights: final dossier for handover, checklist driven testing and support to CEIG inspection. Used by industrial substations, renewable parks and lender completion. Delivered in line with IEC 62446-1, IS 3043 and IEC 61557. Mobilisation On-site 3-21 days; serves All India. Sample listing: illustrative data for testing BARREL Shop, not a real offer.

Brand
Kamrup
Model
KAM-1A9 series
Listing type
Service
Unit
site
Minimum order
1 site
Lead time
On-site 3-21 days
Warranty
Retest at no cost on instrument error
Standards
IEC 62446-1, IS 3043, IEC 61557
Delivers to
All India
GST rate
18 %
Country of origin
India
Delivery terms
Site mobilisation as per work order
Returns
Re-work of defective scope at no cost
Other terms
Sample data for testing; not a real offer.

Variants

VariantSpecificationsMin. order · lead timePrice, ex GST
Plant size5 MWKAM-1A9-01Plant size: 5 MW1 site · On-site 3-21 daysfor verified buyers
Plant size10 MWKAM-1A9-02Plant size: 10 MW1 site · On-site 3-21 daysfor verified buyers
Plant size25 MWKAM-1A9-03Plant size: 25 MW1 site · On-site 3-21 daysfor verified buyers
Plant size50 MWKAM-1A9-04Plant size: 50 MW1 site · On-site 3-21 daysfor verified buyers
Plant size100 MWKAM-1A9-05Plant size: 100 MW1 site · On-site 3-21 daysfor verified buyers

Specifications

Plant size5 MW to 100 MW (see variants)
ScopeElectrical pre-commissioning
InstrumentsRelay test set, IV tracer, CRM
Test sequencePer client approved format
TeamTeam of 6 with leadmade to order: Test engineer plus 2 technicians
Duration on site10 days
ReportsDigital dossier with photosmade to order: Test results on approved formats
CalibrationCalibration certificates attachedmade to order: NABL traceable
Witnessed byClient engineermade to order: Lender engineer or authority
Retest policyOne retest included
PaymentOn completion of reportmade to order: 50% advance