Catalogue / Cabling, trenching & HDD works
Cable trenching and laying for power and control cables, Xtra 2 seriesSample
by Nilgiri Infra Services (Sample) · verified by BARREL
Price for verified buyers
Ordered and invoiced through BARREL — one contract, one GST invoice.
Customise and request quoteMade to order: change the marked specification rows to what you need; Nilgiri Infra Services (Sample) quotes for it.
Or send an open RFQ to every matching merchant.
Register your company to see prices.
The Xtra 2 service of cable trenching and laying for power and control cables by Nilgiri covers 6 cable route length options (1 km to 50 km). Key features: warning tape and marker installation, utility locating before excavation and HDD bore log and as-built survey. Typically used for industrial plant cabling, urban distribution upgrades and railway and highway crossings. Delivered in line with IS 1255 (Cable Installation), IS 7098 (XLPE Cables) and IEC 60840. Mobilisation Mobilisation in 7 days; serves East & North-East India. Sample listing: illustrative data for testing BARREL Shop, not a real offer.
- Brand
- Nilgiri
- Model
- NIL-B58 series
- Listing type
- Service
- Unit
- km
- Minimum order
- 1 km
- Lead time
- Mobilisation in 7 days
- Warranty
- Restoration warranty 6 months
- Standards
- IS 1255 (Cable Installation), IS 7098 (XLPE Cables), IEC 60840
- Delivers to
- East & North-East India
- GST rate
- 18 %
- Country of origin
- India
- Delivery terms
- Site mobilisation as per work order
- Returns
- Re-work of defective scope at no cost
- Other terms
- Sample data for testing; not a real offer.
Variants
| Variant | Specifications | Min. order · lead time | Price, ex GST |
|---|---|---|---|
| Cable route length1 kmNIL-B58-01 | Cable route length: 1 km | 1 km · Mobilisation in 7 days | for verified buyers |
| Cable route length2 kmNIL-B58-02 | Cable route length: 2 km | 1 km · Mobilisation in 7 days | for verified buyers |
| Cable route length5 kmNIL-B58-03 | Cable route length: 5 km | 1 km · Mobilisation in 7 days | for verified buyers |
| Cable route length10 kmNIL-B58-04 | Cable route length: 10 km | 1 km · Mobilisation in 7 days | for verified buyers |
| Cable route length20 kmNIL-B58-05 | Cable route length: 20 km | 1 km · Permits may extend timeline | for verified buyers |
| Cable route length50 kmNIL-B58-06 | Cable route length: 50 km | 1 km · Permits may extend timeline | for verified buyers |
Specifications
| Cable route length | 1 km to 50 km (see variants) |
|---|---|
| Method | Trenchless HDDmade to order: Open trench / Trench plus HDD for crossings |
| HDD capacity | Up to 450 mm boremade to order: Up to 250 mm bore |
| Trench depth | 1.2 mmade to order: 0.9 m / 1.5 m |
| Cable type | LT armouredmade to order: 11/33 kV XLPE |
| Jointing | Premoulded |
| Restoration | Backfill and compaction only |
| Permissions | Client arrangesmade to order: Contractor arranges road cut approvals |
| Testing | Insulation and VLF testmade to order: Hipot and sheath test |
| Productivity | 50 m per day HDD |
| Crew | Trenching team of 15 |