Catalogue / Installation & erection
Cable laying, termination and earthing installation, Ultra seriesSample
by Nilgiri Technical Services (Sample) · verified by BARREL
Price on quote
Ordered and invoiced through BARREL — one contract, one GST invoice.
Customise and request quoteMade to order: change the marked specification rows to what you need; Nilgiri Technical Services (Sample) quotes for it.
Or send an open RFQ to every matching merchant.
The Ultra service of cable laying, termination and earthing installation by Nilgiri covers 3 installation scope options (1 MW to 10 MW). Key features: torque-verified structure and module fixing, punch list closure before testing and cable route marking and tray fixing. Used by c&I rooftop and ground mount, utility solar parks and wind farm substations. Delivered in line with IS 732 (Electrical Wiring), IEC 62548 and CEA (Measures relating to Safety) Regulations. Mobilisation Start after material at site; serves All India. Sample listing: illustrative data for testing BARREL Shop, not a real offer.
- Brand
- Nilgiri
- Model
- NIL-DD4 series
- Listing type
- Service
- Unit
- MW
- Minimum order
- 1 MW
- Lead time
- Start after material at site
- Warranty
- Defect liability 24 months
- Standards
- IS 732 (Electrical Wiring), IEC 62548, CEA (Measures relating to Safety) Regulations
- Delivers to
- All India
- GST rate
- 18 %
- Country of origin
- India (imported sub-assemblies)
- Delivery terms
- Site mobilisation as per work order
- Returns
- Re-work of defective scope at no cost
- Other terms
- Sample data for testing; not a real offer.
Variants
| Variant | Specifications | Min. order · lead time | Price, ex GST |
|---|---|---|---|
| Installation scope1 MWNIL-DD4-01 | Installation scope: 1 MW | 1 MW · Start after material at site | on quote |
| Installation scope5 MWNIL-DD4-02 | Installation scope: 5 MW | 1 MW · Start after material at site | on quote |
| Installation scope10 MWNIL-DD4-03 | Installation scope: 10 MW | 1 MW · Start after material at site | on quote |
Specifications
| Installation scope | 1 MW to 10 MW (see variants) |
|---|---|
| Scope | Structure and module installationmade to order: Electrical BoP erection / Complete mechanical and electrical erection |
| Manpower deployed | 60 technicians plus supervisors |
| Supervision | Project manager, engineers, QA/QC |
| Equipment | Pile driver, crane, telehandler |
| Quality plan | ISO 9001 QAP with hold points |
| Safety | Lost-time-injury-free target, HIRA |
| Licence | Class A contractor registrationmade to order: Electrical contractor licence |
| Insurance | CAR and workmen compensationmade to order: CAR, WC and third-party liability |
| Reporting | Daily progress reportmade to order: Weekly report with look-ahead plan |
| Payment terms | Monthly running billsmade to order: Milestone based with 10% retention |