Third-party inspection (TPI)Vidyutline5 variants
SampleServiceThird-party inspection (TPI) Vidyutline · VID-095 series
- Inspection effort
- 1 man-day to 50 man-days (see variants)
- Equipment inspected
- Cables and conductors
- Inspection stage
- In-process
- Standards used
- Per approved QAP
- Inspector qualification
- B.E. Electrical with 8 years experience
Lead time Inspector assigned in 48 hours · Warranty As per contract · MOQ 1 day
Type & routine testing laboratories (NABL)Kakatiya5 variants
SampleServiceType & routine testing laboratories (NABL) Kakatiya · KAK-9B1 series
- Test class
- Special test to Short-circuit test (see variants)
- Equipment under test
- PV modules
- Accreditation
- NABL plus BIS recognition
- Rating range
- Up to 33 kV
- Test standard
- IS or IEC as specified
Lead time Test report in 3-8 weeks · Warranty Free retest on lab error · MOQ 1 nos
Site acceptance & pre-commissioning testsDeccan4 variants
SampleServiceSite acceptance & pre-commissioning tests Deccan · DEC-241 series
- Plant size
- 10 MW to 100 MW (see variants)
- Scope
- Electrical pre-commissioning
- Instruments
- Relay test set, IV tracer, CRM
- Test sequence
- Per client approved format
- Team
- Test engineer plus 2 technicians
Lead time Mobilisation in 3-7 days · Warranty Retest at no cost on instrument error · MOQ 1 site
Third-party inspection (TPI)Kamrup3 variants
SampleServiceThird-party inspection (TPI) Kamrup · KAM-961 series
- Inspection effort
- 10 man-days to 50 man-days (see variants)
- Equipment inspected
- Towers and structures
- Inspection stage
- In-process
- Standards used
- Per approved QAP
- Inspector qualification
- B.E. Electrical with 8 years experience
Lead time Inspector assigned in 48 hours · Warranty Re-inspection at no cost for disputed lots · MOQ 1 day
Factory acceptance test (FAT) witnessingMaduraisurya3 variants
SampleServiceFactory acceptance test (FAT) witnessing Maduraisurya · MAD-171 series
- Equipment value
- INR 5 crore to INR 25 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine tests per IS or IEC
- Team
- Specialist engineers per discipline
- Location
- International factory
Lead time Report within 2 days of test · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Site acceptance & pre-commissioning testsMaduraisurya6 variants
SampleServiceSite acceptance & pre-commissioning tests Maduraisurya · MAD-242 series
- Plant size
- 5 MW to 250 MW (see variants)
- Scope
- Electrical pre-commissioning
- Instruments
- Relay test set, IV tracer, CRM
- Test sequence
- Visual, mechanical, electrical
- Team
- Test engineer plus 2 technicians
Lead time On-site 3-21 days · Warranty Report accuracy guaranteed · MOQ 1 site
Electrical safety auditsMaduraividyut5 variants
SampleServiceElectrical safety audits Maduraividyut · MAD-5F9 series
- Installed load
- 500 kVA to 25 MVA (see variants)
- Scope
- Visual and documentation audit
- Auditor
- CEA-licensed engineer
- Measurements
- Thermography and power quality
- Report
- Action plan with timeline
Lead time Audit in 1-2 weeks · Warranty Re-audit at reduced rate · MOQ 1 site
Type & routine testing laboratories (NABL)Maduraisurya4 variants
SampleServiceType & routine testing laboratories (NABL) Maduraisurya · MAD-411 series
- Test class
- Acceptance test to Type test (MV) (see variants)
- Equipment under test
- PV modules
- Accreditation
- NABL ISO/IEC 17025
- Rating range
- Up to 33 kV
- Test standard
- IS or IEC as specified
Lead time Slot in 1-2 weeks · Warranty Free retest on lab error · MOQ 1 nos
Electrical safety auditsKamrup3 variants
SampleServiceElectrical safety audits Kamrup · KAM-5F3 series
- Installed load
- 1 MVA to 10 MVA (see variants)
- Scope
- Visual and documentation audit
- Auditor
- Chartered engineer
- Measurements
- Earth resistance, insulation
- Report
- Action plan with timeline
Lead time Report in 7-14 days · Warranty Re-audit at reduced rate · MOQ 1 site
Factory acceptance test (FAT) witnessingKaverispark6 variants
SampleServiceFactory acceptance test (FAT) witnessing Kaverispark · KAV-9E1 series
- Equipment value
- INR 25 lakh to INR 25 crore (see variants)
- Test plan
- Client approved FAT protocol
- Tests witnessed
- Routine tests per IS or IEC
- Team
- Specialist engineers per discipline
- Location
- Domestic factory
Lead time Report within 2 days of test · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Factory acceptance test (FAT) witnessingUrjatek5 variants
SampleServiceFactory acceptance test (FAT) witnessing Urjatek · URJ-D87 series
- Equipment value
- INR 25 lakh to INR 10 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine tests per IS or IEC
- Team
- Specialist engineers per discipline
- Location
- International factory
Lead time Deployment within 3-5 days · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Product certification (BIS, IEC, ALMM)Shaktimark5 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Shaktimark · SHA-236 series
- Certification scope
- Product family BIS to Multi-standard IEC set (see variants)
- Standards covered
- IS 14286 and IS 16077
- Application support
- Documentation and filing
- Test lab liaison
- Notified bodies
- Factory audit
- Pre-audit gap analysis
Lead time Kick-off in 1 week · Warranty Re-filing support at no extra consulting fee · MOQ 1 application
Factory acceptance test (FAT) witnessingAiravatsys6 variants
SampleServiceFactory acceptance test (FAT) witnessing Airavatsys · AIR-DF1 series
- Equipment value
- INR 25 lakh to INR 25 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine tests per IS or IEC
- Team
- Specialist engineers per discipline
- Location
- Domestic factory
Lead time Report within 2 days of test · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Third-party inspection (TPI)Urjatron6 variants
SampleServiceThird-party inspection (TPI) Urjatron · URJ-6E5 series
- Inspection effort
- 1 man-day to 100 man-days (see variants)
- Equipment inspected
- Transformers and reactors
- Inspection stage
- In-process
- Standards used
- Per approved QAP
- Inspector qualification
- Level II NDT certified
Lead time Inspector assigned in 48 hours · Warranty As per contract · MOQ 1 day
Type & routine testing laboratories (NABL)Kamrup4 variants
SampleServiceType & routine testing laboratories (NABL) Kamrup · KAM-4F4 series
- Test class
- Acceptance test to Type test (MV) (see variants)
- Equipment under test
- Cables
- Accreditation
- NABL ISO/IEC 17025
- Rating range
- Up to 33 kV
- Test standard
- IS or IEC as specified
Lead time Test report in 3-8 weeks · Warranty Report accuracy guarantee · MOQ 1 nos
Factory acceptance test (FAT) witnessingKaveridhruv3 variants
SampleServiceFactory acceptance test (FAT) witnessing Kaveridhruv · KAV-A29 series
- Equipment value
- INR 25 lakh to INR 1 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine plus special tests
- Team
- Specialist engineers per discipline
- Location
- Domestic factory
Lead time Report within 2 days of test · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Factory acceptance test (FAT) witnessingKaverispark3 variants
SampleServiceFactory acceptance test (FAT) witnessing Kaverispark · KAV-9E1 series
- Equipment value
- INR 25 lakh to INR 1 crore (see variants)
- Test plan
- Client approved FAT protocol
- Tests witnessed
- Routine plus special tests
- Team
- Lead engineer and assistant
- Location
- Domestic factory
Lead time Deployment within 3-5 days · Warranty As per contract · MOQ 1 day
Type & routine testing laboratories (NABL)Shaktimark6 variants
SampleServiceType & routine testing laboratories (NABL) Shaktimark · SHA-FB7 series
- Test class
- Acceptance test to Short-circuit test (see variants)
- Equipment under test
- Distribution transformers
- Accreditation
- NABL plus BIS recognition
- Rating range
- Up to 33 kV
- Test standard
- IS or IEC as specified
Lead time Slot in 1-2 weeks · Warranty Free retest on lab error · MOQ 1 nos
Product certification (BIS, IEC, ALMM)Lonavala5 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Lonavala · LON-B41 series
- Certification scope
- ALMM List-I to Full global set (see variants)
- Standards covered
- IEC 62109 for inverters
- Application support
- End-to-end with lab liaison
- Test lab liaison
- Notified bodies
- Factory audit
- Pre-audit gap analysis
Lead time Kick-off in 1 week · Warranty As per contract · MOQ 1 application
Electrical safety auditsUrjatron3 variants
SampleServiceElectrical safety audits Urjatron · URJ-757 series
- Installed load
- 1 MVA to 10 MVA (see variants)
- Scope
- Audit with measurements
- Auditor
- Chartered engineer
- Measurements
- Thermography and power quality
- Report
- Action plan with timeline
Lead time Report in 7-14 days · Warranty Clarifications on report at no cost for 6 months · MOQ 1 site
Product certification (BIS, IEC, ALMM)Mahanadiloha4 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Mahanadiloha · MAH-467 series
- Certification scope
- ALMM List-II (cells) to Full global set (see variants)
- Standards covered
- IEC 62109 for inverters
- Application support
- Documentation and filing
- Test lab liaison
- NABL accredited labs
- Factory audit
- BIS inspection support
Lead time Kick-off in 1 week · Warranty Re-filing support at no extra consulting fee · MOQ 1 application
Electrical safety auditsMaduraisurya4 variants
SampleServiceElectrical safety audits Maduraisurya · MAD-887 series
- Installed load
- 5 MVA to 50 MVA (see variants)
- Scope
- Audit with arc-flash study
- Auditor
- CEA-licensed engineer
- Measurements
- Earth resistance, insulation
- Report
- Action plan with timeline
Lead time Report in 7-14 days · Warranty Clarifications on report at no cost for 6 months · MOQ 1 site
Type & routine testing laboratories (NABL)Dwaraka4 variants
SampleServiceType & routine testing laboratories (NABL) Dwaraka · DWA-4F4 series
- Test class
- Type test (LV) to Short-circuit test (see variants)
- Equipment under test
- Power transformers
- Accreditation
- NABL ISO/IEC 17025
- Rating range
- Up to 400 kV
- Test standard
- IS or IEC as specified
Lead time Test report in 3-8 weeks · Warranty Free retest on lab error · MOQ 1 nos
Factory acceptance test (FAT) witnessingKakatiyarajat4 variants
SampleServiceFactory acceptance test (FAT) witnessing Kakatiyarajat · KAK-D82 series
- Equipment value
- INR 50 lakh to INR 10 crore (see variants)
- Test plan
- Client approved FAT protocol
- Tests witnessed
- Routine plus special tests
- Team
- Specialist engineers per discipline
- Location
- Domestic factory
Lead time Deployment within 3-5 days · Warranty As per contract · MOQ 1 day