Factory acceptance test (FAT) witnessingUrjatron3 variants
SampleServiceFactory acceptance test (FAT) witnessing Urjatron · URJ-9E9 series
- Equipment value
- INR 1 crore to INR 10 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine tests per IS or IEC
- Team
- Specialist engineers per discipline
- Location
- International factory
Lead time Report within 2 days of test · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Site acceptance & pre-commissioning testsLonavala6 variants
SampleServiceSite acceptance & pre-commissioning tests Lonavala · LON-243 series
- Plant size
- 1 MW to 100 MW (see variants)
- Scope
- Electrical pre-commissioning
- Instruments
- Relay test set, IV tracer, CRM
- Test sequence
- Visual, mechanical, electrical
- Team
- Team of 6 with lead
Lead time On-site 3-21 days · Warranty Retest at no cost on instrument error · MOQ 1 site
Factory acceptance test (FAT) witnessingDwaraka4 variants
SampleServiceFactory acceptance test (FAT) witnessing Dwaraka · DWA-D86 series
- Equipment value
- INR 50 lakh to INR 10 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine plus special tests
- Team
- Specialist engineers per discipline
- Location
- International factory
Lead time Deployment within 3-5 days · Warranty Re-witness at no cost if protocol changes · MOQ 1 day
Third-party inspection (TPI)Airavatsys5 variants
SampleServiceThird-party inspection (TPI) Airavatsys · AIR-091 series
- Inspection effort
- 5 man-days to 100 man-days (see variants)
- Equipment inspected
- Transformers and reactors
- Inspection stage
- In-process
- Standards used
- Per approved QAP
- Inspector qualification
- B.E. Electrical with 8 years experience
Lead time Report in 24-48 hours · Warranty As per contract · MOQ 1 day
Product certification (BIS, IEC, ALMM)Urjatron3 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Urjatron · URJ-B82 series
- Certification scope
- Single product BIS to ALMM List-I (see variants)
- Standards covered
- IEC 62109 for inverters
- Application support
- Documentation and filing
- Test lab liaison
- NABL accredited labs
- Factory audit
- BIS inspection support
Lead time 8-24 weeks for certificate · Warranty Re-filing support at no extra consulting fee · MOQ 1 application
Product certification (BIS, IEC, ALMM)Lonavala5 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Lonavala · LON-B42 series
- Certification scope
- Product family BIS to Multi-standard IEC set (see variants)
- Standards covered
- IEC 61215 and 61730
- Application support
- End-to-end with lab liaison
- Test lab liaison
- NABL accredited labs
- Factory audit
- BIS inspection support
Lead time Kick-off in 1 week · Warranty As per contract · MOQ 1 application
Type & routine testing laboratories (NABL)Urjatek4 variants
SampleServiceType & routine testing laboratories (NABL) Urjatek · URJ-FB6 series
- Test class
- Type test (LV) to Short-circuit test (see variants)
- Equipment under test
- Insulators
- Accreditation
- NABL plus BIS recognition
- Rating range
- Up to 400 kV
- Test standard
- Customer specific test plan
Lead time Test report in 3-8 weeks · Warranty Free retest on lab error · MOQ 1 nos
Site acceptance & pre-commissioning testsShaktimark5 variants
SampleServiceSite acceptance & pre-commissioning tests Shaktimark · SHA-1A5 series
- Plant size
- 10 MW to 250 MW (see variants)
- Scope
- Complete SAT with performance test
- Instruments
- Insulation tester, earth tester
- Test sequence
- Visual, mechanical, electrical
- Team
- Team of 6 with lead
Lead time On-site 3-21 days · Warranty Retest at no cost on instrument error · MOQ 1 site
Third-party inspection (TPI)Mahanadiloha5 variants
SampleServiceThird-party inspection (TPI) Mahanadiloha · MAH-6E1 series
- Inspection effort
- 5 man-days to 100 man-days (see variants)
- Equipment inspected
- Switchgear and relays
- Inspection stage
- In-process
- Standards used
- Per client specification
- Inspector qualification
- Level II NDT certified
Lead time Report in 24-48 hours · Warranty As per contract · MOQ 1 day
Electrical safety auditsAiravatsys3 variants
SampleServiceElectrical safety audits Airavatsys · AIR-2D3 series
- Installed load
- 500 kVA to 5 MVA (see variants)
- Scope
- Visual and documentation audit
- Auditor
- CEA-licensed engineer
- Measurements
- Earth resistance, insulation
- Report
- Action plan with timeline
Lead time Audit in 1-2 weeks · Warranty Re-audit at reduced rate · MOQ 1 site
Factory acceptance test (FAT) witnessingMahanadi4 variants
SampleServiceFactory acceptance test (FAT) witnessing Mahanadi · MAH-DF7 series
- Equipment value
- INR 1 crore to INR 25 crore (see variants)
- Test plan
- Based on tender specification
- Tests witnessed
- Routine plus special tests
- Team
- Specialist engineers per discipline
- Location
- Domestic factory
Lead time Report within 2 days of test · Warranty As per contract · MOQ 1 day
Type & routine testing laboratories (NABL)Dwaraka3 variants
SampleServiceType & routine testing laboratories (NABL) Dwaraka · DWA-4F8 series
- Test class
- Type test (MV) to Short-circuit test (see variants)
- Equipment under test
- Cables
- Accreditation
- NABL ISO/IEC 17025
- Rating range
- Up to 400 kV
- Test standard
- IS or IEC as specified
Lead time Slot in 1-2 weeks · Warranty Report accuracy guarantee · MOQ 1 nos
Third-party inspection (TPI)Kaverispark6 variants
SampleServiceThird-party inspection (TPI) Kaverispark · KAV-216 series
- Inspection effort
- 1 man-day to 100 man-days (see variants)
- Equipment inspected
- Towers and structures
- Inspection stage
- Final pre-dispatch
- Standards used
- Per client specification
- Inspector qualification
- B.E. Electrical with 8 years experience
Lead time Inspector assigned in 48 hours · Warranty As per contract · MOQ 1 day
Product certification (BIS, IEC, ALMM)Kaverispark4 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Kaverispark · KAV-237 series
- Certification scope
- Single product BIS to ALMM List-II (cells) (see variants)
- Standards covered
- IEC 61215 and 61730
- Application support
- End-to-end with lab liaison
- Test lab liaison
- Notified bodies
- Factory audit
- Pre-audit gap analysis
Lead time 8-24 weeks for certificate · Warranty Re-filing support at no extra consulting fee · MOQ 1 application
Type & routine testing laboratories (NABL)Deccan6 variants
SampleServiceType & routine testing laboratories (NABL) Deccan · DEC-9B3 series
- Test class
- Acceptance test to Short-circuit test (see variants)
- Equipment under test
- Switchgear
- Accreditation
- NABL plus BIS recognition
- Rating range
- Up to 33 kV
- Test standard
- Customer specific test plan
Lead time Test report in 3-8 weeks · Warranty Free retest on lab error · MOQ 1 nos
Factory acceptance test (FAT) witnessingMalwavolt5 variants
SampleServiceFactory acceptance test (FAT) witnessing Malwavolt · MAL-175 series
- Equipment value
- INR 50 lakh to INR 25 crore (see variants)
- Test plan
- Client approved FAT protocol
- Tests witnessed
- Routine tests per IS or IEC
- Team
- Lead engineer and assistant
- Location
- Domestic factory
Lead time Report within 2 days of test · Warranty As per contract · MOQ 1 day
Electrical safety auditsMahanadi5 variants
SampleServiceElectrical safety audits Mahanadi · MAH-5F7 series
- Installed load
- 1 MVA to 50 MVA (see variants)
- Scope
- Audit with measurements
- Auditor
- Chartered engineer
- Measurements
- Thermography and power quality
- Report
- Action plan with timeline
Lead time Audit in 1-2 weeks · Warranty Re-audit at reduced rate · MOQ 1 site
Electrical safety auditsKakatiyarajat4 variants
SampleServiceElectrical safety audits Kakatiyarajat · KAK-683 series
- Installed load
- 5 MVA to 50 MVA (see variants)
- Scope
- Visual and documentation audit
- Auditor
- Chartered engineer
- Measurements
- Earth resistance, insulation
- Report
- Findings with risk rating
Lead time Audit in 1-2 weeks · Warranty Re-audit at reduced rate · MOQ 1 site
Electrical safety auditsUrjatek4 variants
SampleServiceElectrical safety audits Urjatek · URJ-5F8 series
- Installed load
- 5 MVA to 50 MVA (see variants)
- Scope
- Audit with arc-flash study
- Auditor
- CEA-licensed engineer
- Measurements
- Earth resistance, insulation
- Report
- Action plan with timeline
Lead time Audit in 1-2 weeks · Warranty Clarifications on report at no cost for 6 months · MOQ 1 site
Electrical safety auditsVidyutline3 variants
SampleServiceElectrical safety audits Vidyutline · VID-758 series
- Installed load
- 10 MVA to 50 MVA (see variants)
- Scope
- Audit with arc-flash study
- Auditor
- CEA-licensed engineer
- Measurements
- Earth resistance, insulation
- Report
- Action plan with timeline
Lead time Audit in 1-2 weeks · Warranty Clarifications on report at no cost for 6 months · MOQ 1 site
Product certification (BIS, IEC, ALMM)Kaveridhruv5 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Kaveridhruv · KAV-239 series
- Certification scope
- Single product BIS to IEC 61215 and 61730 (see variants)
- Standards covered
- IEC 61215 and 61730
- Application support
- Documentation and filing
- Test lab liaison
- NABL accredited labs
- Factory audit
- Pre-audit gap analysis
Lead time 8-24 weeks for certificate · Warranty As per contract · MOQ 1 application
Product certification (BIS, IEC, ALMM)Kakatiya3 variants
SampleServiceProduct certification (BIS, IEC, ALMM) Kakatiya · KAK-553 series
- Certification scope
- IEC 61215 and 61730 to Full global set (see variants)
- Standards covered
- IS 14286 and IS 16077
- Application support
- Documentation and filing
- Test lab liaison
- Notified bodies
- Factory audit
- BIS inspection support
Lead time Kick-off in 1 week · Warranty Re-filing support at no extra consulting fee · MOQ 1 application
Electrical safety auditsMaduraisurya5 variants
SampleServiceElectrical safety audits Maduraisurya · MAD-883 series
- Installed load
- 500 kVA to 25 MVA (see variants)
- Scope
- Audit with measurements
- Auditor
- Chartered engineer
- Measurements
- Thermography and power quality
- Report
- Action plan with timeline
Lead time Audit in 1-2 weeks · Warranty Clarifications on report at no cost for 6 months · MOQ 1 site
Electrical safety auditsMalwavolt4 variants
SampleServiceElectrical safety audits Malwavolt · MAL-2D5 series
- Installed load
- 1 MVA to 25 MVA (see variants)
- Scope
- Audit with arc-flash study
- Auditor
- Chartered engineer
- Measurements
- Thermography and power quality
- Report
- Findings with risk rating
Lead time Report in 7-14 days · Warranty Clarifications on report at no cost for 6 months · MOQ 1 site